Supreme Court

Decision Information

Decision Content

492; iETNX . CSSUALTY '& SURETY' 00.-V::1-TENSLEE: ETA CAStALTY & SUii:ETY COlViPANY -1). 'EUNSLEE. Opinion delivered April 7,•1924. HIGHWAYSCONTRACTOR'S BormLIABILITY. Under Crawford & s ivioses' 6913;prOviding that contractors engaged on public workg exeerité a 'bond eoriditioned to pay for labor perfOrmed or' materials furnished, held - that .the bond of a contractor'-inures to the benefit of those furnThhing labor and materials. . 2. HIGHWAYSCONTRACTOR'S BOND.—A bond for labor aro materials given by the principal dontractor to a road improvement district, which was organized under the general statutes providing for the creation and establishment of road improvement districts, . was given under Crawford & Moses' Dig., § 5446. I - -IIIGHWASCONTRACTOR'S._ BONDA -r et ' regniring '. con- -tr ,• a ctorS te-- give bonds . to secure 'persons - furnishing q abor dha materiali ' are: intended- te furnish the obligatiein of a 'bond as 'a substitute for the security which might be obtained by a mechanic's lien; such liens not being given in the case of public : . works. .. 4.. - HIGHWAYS-CONTRACTOR'S BONDLIABILITY TO SUBCONTRACTOR.— , Under a bond given hy a principal contractor to a road improvement distriet .in compliance with Crawford & Moses' big., § 5446, the 'surety is liable on the failure of the' contractor to pay a subbontractor for labor performed and materials furnished in-the eonstructión of -a proposed road. ' 5. ' HIGHWAYS CONTRACTOWS:BONDPAliTIES. LUn:der § 1089, Craw-•• ford &, Moses', big., providing that- every- action must be prose-- ,.cuted . in the name of the.real party, in interest, a subcontractor who furnished labor arid materials for, building a public road may sue_in his own . name on the . contractor's bond. 6. HIGHWAYSCONTRACTOR'S BONDPARTIES.—Crawford & Moses' Dig., § 5446, providing that any person supplying .labor and materials shall have a right of action and may sue in the name of the road district, does not preclude the person for whose - benefit the statute was enacted from suing in his own name. 7. JUDGMENTPRINCIPAL AND SURETY.—In an action by a subcon- tractor against a- surety on the contractor's i?ond- for_ failure of the contractór to pay far, labor a y n d material" used . in building.a . . yublic . road; the court did .not . err .in , anowing t •. o " .1/2 D % e read To the juriT a dee'ree obtaiii -ed in the 'chancery -ebUrt by the Subcontractor against the contractor, though the surety was not a. party to that suit, such decree being prima facie evidence of a breach of the bond.
1:iiii -CA8tAiii -Y4,7-S-UiriEi-Y -HENSLEE.- 493 . 8. - HIGHWAYSCONTRACTOR'S .BONDSUFFICIENCY OF EyIDENCE OF BREACH.—In . an action by a subeoniractor against the surety on the contractor's bond for labor and maierials furnished in the building of a ioad, 'evidence held- to show that the subcontractor had- substantially complied with his contract. 9. ' HIGHWAYS LIAMLITY OF CONTRACTOR TO SUBCONTRACTOR.—Where the work done by a subcontract6r ' under' his contract substantially -corhrilied With- his cozintract, he.is entitled to recover the contract price,_ less the fair cost of' remedying any defects in the work. - . 10. APPEAL AND ERRORCONCLUSIVENESS OF VERDICT.—Where the * jury's Verdict has evidence of a sUbstantial character to support it, it is binding upon the appellate court. 11. HIGHWAYSCONTRACTOR'S BONDLIABILITY OF SURETY FOR GOSTS. In an action by a subcontractor against a surety of the principal contractor for labor and materials furnished in the building of a road, it was error to allow to the subcontractor against the surety the costs of a former suit against the contractor to which the surety was not a party. APpeal frOin Jefferson Circuit Court ; T. G. Parham, Judge ; ihodifi'ed; - - - STA.TEMENT 424' -FACTS. This is an ' action broUght bi r a . snbeontractor against the principal . contractor and the' Sureties on his bond for work done . and rnaterialS' . furnished in constructing an improved road for ail IliaproverhOnt _district in Woodruff 'County, Arkansas. - The Cotton Plant Road Improvement DiStfici N o ' . 1 'of Woodruff ConntY, -Arkansas,- was Organized under the general laws of the State relating to road improvement districts. R. Mobley entered int6' a cOntract with the commissioners for the constriiction of the road in August, 1917. The 'Etna Casualty and Surety Company signed ' liiS bond in the sum of $40,000 for the faithful per-. forniance of his contraCt and f6r the payment of all labor and Materials entering in the construction of said road. In SepteMber,- 1917; E. A. Henslee, as subcontractor, entered intO a 'cOntraa 'with R: Mobley, the principal contractor, by. the fernis 6f which he agreed to furnish ail toOls, lnbor ' and'eqniptnent and do all the WOilv;fieces-sary to prepare a crushed rock base for an asPhaltic top
494 YETNA CASUALTY & SURETY CO. V. HENSLEE. [163 for the road to be improved. Their contract provided that the payment for the work done by the subcontractor was to be made, at the prices set out in their contract, at the times the principal contractor received payment from the commissioners of the road improvement district upon monthly estimates. In August, 1918, R. Mobley refused to make the payments, because he insisted that Henslee had breached the contract by refusing to repair the rock base, which had become worn, and to put it in shape so that the asphalt surface might be laid on it, and because Henslee would not bring up the shoulders of the road in the manner provided in the contract between Mobley and the commissioners of the road district. Henslee refused to do this work because the rock base had become worn by the traffic and weather, due to the delay of Mobley in spreading the asphalt upon the rock base when it had been finished by Henslee. Henslee refused to round up the shoulders of the road, because that was not his duty under the terms of his contract. Testimony was introduced by each party to sustain his contention. Other facts will be stated in the opinion. The cause was tried before a jury, which returned a verdict in favor of the plaintiff, and from the ,judgment rendered the defendants have _duly prosecuted an appeal to this court. J. H. Carmichael and J. A. Sherrill, for appellant. The suit should have been brought in the name of the district. Appellee relied on act 446 of the Acts of 1911, in bringing the suit in his own name, whereas act 338 of the Acts of 1915 repeals the former act, so far as relates to roads. 149 Ark. 576. The execution of the bond required by the 1911 act is mandatory. 159 Ark. 275. If the action must be maintained under § 5446, C. & M. Digest (Acts 1915), then appellee must follow that statute to be entitled to the relief provided for, and maintain the same in the name of the district ; having failed to do this, his suit should be dismissed. 82 Ark. 407; 82 Ark. 247 ; 153 Ark. 321. Even if both § 6913 (Act
ARK.] IETNA CASUALTY & SURETY CO. v. HENSLEE. 495 1911) and § 5446 are available to road districts, appellee should seek his relief under the same statute followed by the district. If the suit was brought under § 6913, relating to those who furnish la:bor and material, it should be dismissed, since appellee did neither. 65 Ark. 183 ; 102 Ark. 539; 125 Ark. 590 ; 159 Ark. 21. The fact that a borrower used Money loaned to pay persons having a mechanic's lien does not subrogate the lender to such lienor's rights. 155 Ark. 201 ; 158 Ark. 137. It :was prejudicial to introduce the judgment obtained in the former suit, since the surety was not .a party thereto. 147 Ill. 634, 35 N. E. 820 ; 21 R. C. L. 1090. A. F. Triplett, for appellee. A judgment against a principal is prima facie evidence in a suit against his surety. 89 Ark. 378; 98 Ark. 143; note 16 L. R. A. (N. S.) 911. A construction bond to an improvement district inures to the benefit of a person furnishing the contractor with labor and materials, where the bond contains appropriate provisions with reference to such labor and materials. .126 Ark. 474; 152 Ark. 414 ; 153 Ark. 142. A subcontractor is a person furnishing labor or materials, and can claim the benefit of such a bond. 152 Ark. 414; note 27 L. R. A. :(N. S.) 573. It iS the policy of our law that a suit should be prosecuted th .the name of the real party in interest, and the statute to this effect, § 1089, C. & M. Digest, is to be : read along with § 5446. Section 5446 does not repeal 1089, nor provide an exclusive remedy. HART, J., (after stating the facts). Inasnauch as the cause of actiOn of the plaintiff is based upon a statutory bonct for work done in the construction of a pane road by an improvement district, we have deethed it appropriate to give a brief history of statutes of this sort and our : decisions construing the same. Section 6913 of Crawford & Moses' Digest, which was passed by the Legislature of 1911, provides that, whenever any public officer shall, under the laws : of this State, enter into a contract with any, person ' fOr the purpose of making any-public improvement, or constructing
496 ATNA CASUALTY & SURETY CO. v. HENSLEE. [163 any public building, such officer shall take from the principal contractor a bond with sufficient sureties, conditioned that such contractor shall pay all the indebtedness for labor and materials furnished in the construction of said public building or in making said public improve ment. This court has held that school directors and commissioners of road districts are public officers, and that -the bond of the contractor given under the statute inures to the benefit of those furnishing labor and materials, and that an action may be maintained thereon by one of such persons for labor performed, or materials supplied in the construction of a schoolhouse or an improved public road. Reiff v. Redfield School Board, 126 Ark. 474; Oliver Construction .Co. v. Williams, 152 Ark. 414; and Arkansas Road Const. Co. v. Evans, 153 Ark. 142. In the two cases last cited special acts of the Legislature had been enacted creating the road improvement districts, and the acts contain no provisions providing for the execution of a bond by the principal contractor to pay subcontractors and other persons furnishing labor and materials for the construction of the improved road, and the court held that the provisions of § 6913 were broad enough to include laborers who have performed work on the road proposed to be improved, or those who have furnished materials which the principal contractor had obligated himself to furnish. The record in the case at bar shows that the road district was organized under the general statutes of this State providing for the creation and establishment of road improvement districts. This act was passed by the Legislature of 191 and . § 5446 ',of Crawford & Moses' Digest is § 30 of the act. It reads as follows: `'All contractors shall be reouired to, give bond for the faithful Performance of such contracts as may be awarded to them, with good and sufficient security in an amount to be fixed by the board of commissioners. and said bond shall contain an additional obligation that such contractor, or contractors, shall promptly make payment to
ARK.] "ETNA CASUALTY & SURETY CO. v. HENSLEE. - 497 all persons supplying him or them labor and materials in the prosecution of work provided for in such contract. Suit may be brought by and in the name of the- district upon the bond given to the board. Any person, individual or corporation supplying labor and material shall have the right of action, and shall be authorized to bring suit in the name of the district for his, their, or its use and benefit, against said contractor and surety, and to prosecute same to final judgment and execution, but such action and its prosecution shall involve the district in no expense whatsoever." Inasmuch as the improvenient district in question was organized under the general laws of the State, it results that the bond given by the principal contractor was given in compliance with the terms of § 5446 of the Digest quoted above. The bond sued on was given for two purposes. In the first place, it was given to secure to the commissioners of the district the faithful performance of the contract of the principal contractor . with the district ; and, in the second place, to protect third persons from whom the contractor may obtain materials or labor used in the construction of the improved road. Acts of this kind are intended to furnish the . obligation of a bond as a substitute for the security which might be obtained by a mechanic's lien, such liens not being given in the case of public works. The purpose of the Legislature in providing security for the payment for labor and materials going in the construaion of an improved, public road was intended to provide indemnity to persons furnishing such labor or materials, thereby enabling the Principal contractor to meet his contracts with road improvement districts in . supplying the _labor and materials necessary to the construction of the propoSed road. In construing a similar statute p assed by_ Congress, the Su preme Court of the United States bas held that work done and materWs - furnished by subcontractors come within the provisions . of the statute, and that they are protected by it. Guaranty do. v. Pressed Brick Co.:
498 /ETNA CASUALTY & SURETY CO. V. HENSLEE. [163 191 U. S. 416, and Mankin v. United States, 215 U. S. 533. In hill v. American Surety Co., 200 U. S. 197, the protection of the statute was extended to materials furnished to subcontractors. Inasmuch as persons furnishing materials and labor used in the construction of an improved public road cannot secure themselves by a mechanic's lien upon the proposed improvement, the Legislature, for the protection of these persons, passed a statute fbr the prompt payment of their claims and the same security that it requires for the faithful performance of the contract of the principal contractor with the commissioners of the district. The surety company was organized for the purpose of furnishing bonds of this kind. It understands perfectly well the nature and extent of its obligation, and its liability is fixed by the terms of the bond, construed in connection with the act of the Legislature in compliance with which the bond is executed. This is the effect of our own decision in the case of Kerby v. Road Improvement Dist. No. 4 Saline County, 159 Ark. 21. In construing § 5446 of the Digest the court said that the benefits of the act were extended to those who supply the labor of others as well as those who labor themselves. Thus subcontractors and those working for them are brought within the provisions of the act. While the statute does not require it, it has been well said that the contractor can protect himself by requiring a bond securing him against liability on account of engagements of the subcontractor with persons who furnish labor and materials upon his order. Therefore we are of the opinion that the terms of the bond make the surety liable for the failure of the contractor to pay the subcontractor for labor performed and materials furnished in the construction of the proposed public road. It is insisted, however, that, under the statute, the subcontractor has no right to bring suit in his own name against the contractor for a : breach of contract. We cannot agree with counsel in this contention. Section 1089
ARK.] }ETNA CASUALTY & SURETY CO. v. HENSLEE. 499 of Crawford & Moses' Digest is a part of our Civil Code, and provides that every action milk be prosecuted in the name of the real party in interest, with certain exceptimis which do not relate to the subject of the controversy in this suit. Since the adoption of the Code, it has been held that actions on bonds given to the State for the faithful performance of the duties of a public officer may be prosecuted by the State, or by the real party in interest that is, by the person entitled to receive the money occasioned by the breach of the official bond. Hunnicutt v. Kirkpatrick, 39 Ark. 172, and State v. Wood, 51 Ark. 205. Subsequently it was held that those er-forming labor or furnishing materials upon a public building for whose benefit the bond required by § 6913 of the Digest referred to above was given, may sue upon the bond, on the principle that a third person for whose benefit a statute requires a bond to be executed may maintain an action thereon although the consideration does not directly move from such third person. Reiff v. Redfield School Board, 126 Ark. 474. But it is claimed that, inasmuch as § 5446 provides that any person supplying labor and materials shall have a right of action and shall be authorized to bring suit in the name of the district for his use against the contractor and his surety, this method is exclusive. While there is some conflict in the authorities on this point, we think that the better reasoning is that the language of the statute is permissive merely, and does not prevent the person for whose benefit the statute was enacted from suing in his own name, under the principles above announced. No prejudice whatever can result to the contractor from this construction. The statute, in providing that the persons supplying labor and materials shall be authorized to bring suit in the name of the district for his use, in effect makes such persons interested parties, and the omission of the name of the district could not in an y , manner prejudice the rights of the contractor. The provision authorizing suit in the name of the district for the use of those supplying labor and materials
500 ' AT14"A-1- Okalf "-& SURETY "- Ca:- v.- HENELEE. * : -R63 merelY provides a-convenient method for styling the case, and . was evidently not intended-to.be the exclusive remedy for its enforcement; - The object of the statute was to give -the -same 'relief by a proceeding -upon the bond as could be had, in the-case of the erection of a 'building by a private OWner,"by_the enforcement of a lien against the building, and, subh being the evident intention of the statute, it Should receive such construction as will render it most effective for that purpose. While the statute ought to be obeyed, yet, inasmuch as it named the district for the . use and benefit of those furnishing labor and materials as_ the plaintiff, it : is to be regarded as directory merely. The condition of the . bond is the important requirement. Of course, where there are several_ claimants who have the - right of -participation, and the funds - should be-insufficient to -pay all parties in full, it might bedome necesSary :t O - make the district a party, so that. the TightS of all -the- parties might -be settled and the distribution of the funds available might be- in proportion to- the amount due to each one. Hence we are of the opinion that the subcontractor, under the provisions of our Code, had the right to maintain the suit in his own name as the real party -in interest. In . the trial . of the case the- cOurt allowed to be read to the jurY cleeree Obtained ifi q he Ch'aiiCery- -court by E. A. HenSlee agai:iisi a Motley tipthithis' same cause of action -. This de -c-ree waS' obtained pursuant to directions giyen revel i §ihg the' decree of the chancery court in the Ca'Se of ifen -slee v. Mobley, 148 Ark. 181. The surety _was not a partY fe that suit, but it was upon the same cauSe of aetion; -aha we are of the opinion that the decree was _properlY adthitted in . evidence . Against the surety in this case. , It ritov-ed: at least a prima facie breach of the bond ty showing the aniouni,dte bY. Motley to ilenslee for a breach -of-the Cohtra4 'which the bend Was given to secure. -Ingle v: Eateville G ' rocery 'CV.," 89: Ark. 379; Baxter Comity" Baia v. .0ark insla. dnce Co., 98 Ark. 143 ; and Mos . es v. United *States, 166 U: S. 571.
, YkRK..1 TNA- CiikTALTY -& SURETY CO. -v. HENSL 501 The -cOurt, : ii itS . -in7Str1Ctiiims- to- the jury, tdid it that the judgment or 'decree against the _principal mc as only ,prima..teic_i4LeVidericyJn.fhe _subsequent suit against the surety,, w! tio: had no; notice or -opportunity to &fend the former :suit. , Henco the :circuit court coMmitted no . error * i _ n a ll _ ow in _ g t his judgment or decree to be read iU eVidence . in the present case. TheinS . true _ t iOnS o _ f the . c . ourt were i . n accord 'rice with the principles of law announced above. It is also insiSted that the evidence is n t legally saficient to SUpport the verdict. As we have jlist seen, the chancery court, pursnant to the directions Of this Court, rendered a decree in favor of -HenS10 against Mobley upon the same cause of action. This jUdgment or decree .was prima facie evidence in a suit baked upon the same cause .of . action against the surety hen the bond of Mobley. In addition to this, other evidehee was introduced by the plaintiff tending to establish his cause of action. It was shown that he performed his bohtract substantially according to its terms, and that the rock base put on the road by him became smooth by the action .of ihe weather and of persons traveling over the road after he had. Completed his work. It was.shown by him " that this was caused-by the delay of the principal con-_tractor in , spreading:the . asphalt surface 'upon the, rock base.. The principal contractor attempted to justify his delay by the action of the .United States Government in requisitioning his machinery which . was to be used in laying the asphalt . surface on the road. His testimony, 'howevef,' i . S flatly ' contradicted . b y . that of an engineer, Who-stated that h ' e NkFas fainiiiar with the whole transac- . anThthat the tnifea . S . t ates Government had not reqUistioned hiS machinery for laying asphalt at the time claimed by the principal contractor: It was also shown by the defendants that the plain-- tiff failed ti5 romid'up the shoulders : of the road after the aSphaIt . surface ' -,On'the 'part of 'the'plaintiff it WiS , ' hown that it was -not his' duty to' do-this work; but" that it devolved upon
502 2ETNA CASUALTY & SURETY CO. V. HENSLEE. ' [163 the principal contractor to do it in connection with laying the asphalt surface of the road. The jury settled the conflicting evidence on these points in favor of the plaintiff. The court told the jury that if it found, from a preponderance of the evidence, that the work done .by Henslee, under his subcontract with Mobley, was done substantially in compliance with the contract, its verdict should be for the contract price of the work done by him, less the fair cost of remedying any defects in the work. This was a correct declaration of law, and the verdict of the jury, having evidence of a substantial character to support it, is binding upon us upon appeal. Finally it is insisted that the court erred in allowing the plaintiff to recover the costs of the suit in the case of Henslee against Mobley, which was introduced in evidence in this case as above stated. The costs in that case amounted to the sum of $342.23, with interest thereon at 6 per cent. from September 11, 1918. The verdict in this case was returned on January 5, 1923. The surety was not made a party to that suit, and was never called upon to defend the same. Hence it should not he charged with the costs of that suit, and the court erred in so instructing the jury. . The verdict of the jury in the present case was for $6,231.63. The error may be eliminated by deducting from this amount the sum of $342.23 with interest thereon from September 11, 1918, to January 5, 1923. The court directs that the remittitur be entered here, and, inasmuch as this is a law ease, the costs of appeal will be adjudged against Henslee. American Soda Fountain Co. v. Battle, 85 Ark. 213; Brown v. Yukon Nat. Bank, 138 Ark. 210 ; and Sweet Springs Milling Co. v. Gentry, 142 Ark. 234. For the error in charging the iEtna Casualty and Surety Company with the costs of the a ppeal in the chancery suit of Henslee against Mobley, the judgment must be reversed. But, inasmuch as the case has been
ARK.] 503 fully developed, judgment will be rendered here in favor of the plaintiff against the surety company for the amount indicated in the opinion. It is so ordered.
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.