Supreme Court

Decision Information

Decision Content

642 GAGE & SPENCER V. ROAD. IMP. DIST. No. 3. [159 GAGE & SPENCER V. ROAD IMPROVEMENT DISTRICT NO. 3. Opinion delivered July 2, 1923. HIGHWAYSCONCLUSIVENESS OF ENGINEER'S ESTIMATE. TJnder a contract for building a road, which provided that the engineer's decisions shall be final and conclusive, the road district is not bound by estimates made by the engineer based on reports of an employee resulting from fraud or gross mistake. 2. HIGHWAYSFRAUD OR M ISTAKE OF ENGINEERJURY QUESTION.— Whether road contractors were overpaid through the engineer's fraud or gross mistake held for the jury. 3. APPEAL AND ERRORMATTERS NOT ABSTRAC EDPRESU M PTIO N.— Where the pleadings, testimony and instructions in a case are not abstracted by appellants, it will be presumed that the issues were Correctly submitted, and that there was testimony sustaining the verdict. 4. H IGH WAYSOVERPAY MENT TO CO NTRACTORSLIABILITY OF SURETY. The surety on a road contractors' bond, binding it to indemnify the improvement district against loss from their negligence in prosecuting the work and failing to pay bills or to complete the work within the time specified, is not liable for money overpaid the contractors through the fraud or gross mistake of the engineer. Appeal from Newton Circuit Court; J. M. Skinn, Judge ; reversed in part. George J. Crump and N. B. Maxey, for appellants. The contract provides that the estimates made by the enghieers are to he conclusive, and is binding on both parties. No fraud is charged against the engineer in charge of the work, nor that he allowed more than the. work was wortb. Case is controlled by 83 Ark. 146,. which is directly in point ; 88 Ark. 213. Appellants were entitled to recover the amount of the final estimates. Even though appellee be iield entitled to recover against the contractors, it can not recover against the surety bond. The judgment against Gage & Spencer should be reversed and judgment given for the engineer's, final estimate, and in any event the judgment against the surety must be reversed and the cause dismissed as to it.
ARK.] GAGE & SPENCER V. ROAD. IMP. DIST. No. 3. 643 E. G. Mitchell, for appellee. The appellee was not 'bound to the payment of the estimates of the engineer, notwithstanding the provision of the contract to that effect, because of the proof of fraud and bad faith on the part of the engineers. 48 ' Ark. 522; 68 Ark. 185 ; 79 Ark. 505; 88 Ark. 213. Wool), J. Gage & Spencer, a partnership (hereafter called appellants) were contractors. They were nonresidents. They entered into a contract with Road Improvement District No. 3 of Newton County, Arkansas (hereafter called appellee), to do work on its road. Appellants istituted tliis action against the appellee for damages and for failure to pay for work done under the contract. The appellee filed a motion to require appellants to make bond for costs, and also a cross-complaint setting up the particulars in which it alleged that the appellants had violated their 'contract, and made the National Surety Company (hereafter called surety company) a defendant. Appellee alleged that the surety company was on appellants' bond for the faithful performance of their contract. The surety company, through its attorneys, entered its appearance. The appellants failed to file their bond, and t heir cause of action was dismissed. Sec. 1845, Crawford & Moses' Digest. It was alleged in the cross-complaint that the appellee had been damaged by failure of appellants to perform their contract in certain particulars, which are specified, in the sum of $2,999.99, for which it prayed judgment 'against the appellants and the surety company. The appellants and the surety company, in their answer to the cross-complaint, denied all the allegations of the cross-complaint, and denied liability. The cause was submitted upon these issues and the testimony adduced at the trial, and the jury returned a verdict in favor of the appellee against the appellants for the amount prayed in the cross-complaint, and against the surety company in the sum of $1,778.77, rrom which judgment the appellants and the surety company appeal.
644 GAGE & SPENCER V. ROAD IMP. DIST. No. 3. [159 The contract between the appellants and the appellee was introduced in evidence. It provided that the appellants should build a road for the appellee according to the plans and specifications, which were made a part of the contract, and the appellee was to pay for the work at the prices stipulated., The appellants were to begin work under the contract on the 21st of Jime and to complete the work within 156 working days after they began. If they failed to complete the work in the time specified they were to pay $15 each day delayed, which Sum was to be liquidaed damages and deducted from the final amount due the appellants under the contract. The bond *bound the surety company, in case of the failure of appellants to perform their contract, to indemnify and save harmless the appellee against any loss or damage Of whatever kind and character, arising or occasioned by deed of negligence of the appellants, their agents, servants and employees, in the p rosecution of the work, or by reason of improper safeguards or incomplete protection to the work, or by reason of failure to pay all bills for material and labor which entered into the construction of the work or used in the course of the performance of the work, and by reason of a failure to complete the work witirin the time specified. The specifications, made a part of the contraat, contained the following provisions : "The engineer shalq-Y,` have full supervision over the entire work, and hi's cision as to qualit3 I, of material, construction and rate of progress of said work and the meaning of all drawings and . specifieations shall be final and conclusive. He shall determine the amount and quantity of work of the several kinds performed, materials furnished which are . to be paid for under the contract. In case any question shall arise (his decision) shall be a condition precedent to the right of the contractor to receive any money due under the contract. All orders and instructions to the contractor shall be given by he engineer." And the further provision that "the final estimate of the
ARK.] GAGE & SPENCER V. ROAD. IMP. DIST. No. 3. 645 engineer should take the place of all prior certificates or estimates upon which payments had been made." The final estimate of the engineer showed that the district was indebted to the appellants in the total sum of $20,821.37, less previous estimates of $17,637.49, leaving a 'balance due appellants of $3,183.88. The appellant's, after setting forth the above as their abstract of the record, further state: "Neither will we abstract the evidence in regard 'to the fraud and collusion charged and attempted to be proved. The only suspicious circumstance shown in that instance is- that Stanley, the engineer in charge of the work, while he was engaged as su3h engineer, also was hired to the contractors to do certain work for them." The 'appellee has abstracted the testimony of R. D. Alexander. He testified that ids company was a corporation, and was employed as engineer of the appellee to superintend the building of the road. He employed 0. A. Stanley as local engineer to _lay out 'the work according to the plans given 'him.. Witness was never ealled on to make a final estimate under the contract with the appellants, but did of the road he worked. He had some sort of report from Stanley. He did not make an estimate from this reportchecked them up, but they did not balance. There was a discrepancy, and then it was that Roberts 'and witness came and calculated it on the ground. The y found matters that caused witness to come himself. In tryinl.); to verif y ; witness took numerous 'observations of the road, and it did not show that Stanley was makhig too large an allowance to Gage & Spencer under the contract. Witness found places where the road was not over eleven feet wide. .The contract called for the road to be sixteen feet wide. Stanley had no rizht to make:a final estimate. WitneRS' com pan y did that. The defect in the road as left by the contractors was deficiency in ditches and p oints of narrow width that were not up to specifications. It had very little valuecould have been 'constructed reia-
646 GAGE & SPENCER /). ROAD IMP. DIST. No. 3. [159 sonably forfrom $2,500 to $3,000 per mile. Witness was on the job while Gage & Spencer were at work on it very seldomone time, possibly twice, not to exceed that. Witness thought that he was there only one time, and spent probably half a day. He had nothing but a tape-line. Witness did not find Stanley's work generally satisfactory. Stanley had no right to work for Gage & Spencer. Witness did not authorize itwould not have authorized him or any other man to do that. Witness Cantrell testified that he was a graduate in engineering of the University of Arkansas; that the contractors had not removed the dirt and rock claimed, and under the contract they had been greatly overpaid. W. M. Moore testified that he was one of the commissioners of the appellee; that the board had overpaid the appellants; that it had paid them $20,000, and they should have been paid for actual work performed under the contract $13,000. Gage testified that before they quit Stanley was in their employ. He worked for us while he had employment from . the other side. Witness took his orders from Stanley absolutely. Stanley did not take orders from witnesS. Stanley 'testified that he acted as foreman in the 'employ of Gage & Spencer in their absence, and some- times when they were present. He got $5 a day; his boy got $3 a day and board. Gage & Spencer fed witness' horse. His brother-in-law got thirty cents an hour, and they fed his horse. The appellee paid witness $125 a month 'and expenses when he was away from 'headquarters. Witness was to look after the construction of the roadto give appellee his time and ability. He had accepted em ployment from the appellee and had been working for the other fellow. Witness never told the commissioners of the district of his employment by Gage & Spencer. The inference of his language to Moore was that he was not in the employ of G-age & Spencer and would not stand under that accusation.
ARK.] GAGE & SPENCER V. ROAD IMP. DIST. No. 3. 647 Spencer testified that Stanley got an automobile from him. If he said that he did not, he was a liar. That was a private transaction between Stanley and witness. Witness sold it to Stanley for Cash. In the cross-complaint filed by the appellee against the appellants it is, among other things, alleged: "They (appellants) conspired and entered corruptly a conspiracy with 0. A. Stanley, then and there employed by R. D. Alexander Engineering Company, by which they undertook to and did claim that they had moved a large number of cubic yards of dirt and broken rock, and claimed the same to be solid rock. By this conspiracy and fraud they did succeed in securing from plaintiff in crass-complaint (appellee) vast sums of money, the amount of which is known to them and unknown to this plaintiff" (appellee), etc. The appellants invoke the doctrine of our cases to the effect that, where the parties to a building contract agree that in disputes between them concerning the provisions of the contract or the performance thereof the decision of the engineer or of the architect shall be final and conclusive, the decision of the engineer or architect under such contract is binding upon the parties to it, and such decision cannot be 'challenged except upon proof of fraud, or such gross mistake as necessarily- implies bad faith on the part of the engineer. Carlile v. Cor-rigan, 83 Ark. 140; Boston Store v. Schleuter, 88 Ark. 213. But the doctrine of these cases cannot avail the appellants, for the reason that they have not abstracted the pleadings, the testimony, or the instructions bearing upon the issue of fraud and gross mistake upon the part of the engineer. The appellants content themselves on this issue by saying: "We will not abstract the evidence in regard to the fraud and collusion charged and attempted to be proved." And again: "There is no allegation of fraud on the part of Alexander, the chief engineer, who made the final estimates in person. The only evidence of mistake is the testimony of other
648 GAGE & SPENCER V. ROAD IMP. DIST. No. 3. [159 engineers and witnesses that the work could have been done for less. This, as quoted above, is not sufficient -to establish fraud or gross mistake." But the appellee, as we have seen, does charge that the appellants "corruptly entered into a conspiracy with 0. A. Stanley, then and there employed by R. D. Alex ander Engineering Company, by which hey defrauded the appellee of vast sums of money," etc. And the appellee, in its abstract, sets forth some testimony tend-Mg to prove that Stanley; the local engineer, was employed by the R. D. Alexander Engineering Company, and that while so employed he also accepted employment from appellants; hence that, through his fraud or gross mistake, the ap pellee had paid out sums largely in excess of what the y should have p aid under the contract. Any fraud or gross mistake of Stanley was the fraud or grass mistake of the chief engineer who employed him, and the appellee therefore was not bound by the estimate made by Stanley or the engineering company predicated up on any reports made by Stanley, that mipbt have been the result of fraud or gross mistake on his part. The- record as abstracted by the appellee is sufficient to show that there was, at least, an issue for the jury as to whether or not the appellants had been overpaid in the sum claimed by the appellee through the fraud or gross mistake of the engineering :oompany, whose decision, under the contract, was made final and conclusive. In the absence of any abstract of the testimony or the instructions upon that issue by the appellants, we. must presume that the issue was correctly submitted by the trial court, and that thOre was testimony to sustain the verdiot. The judgment therefore agai ns , t the appel- lent must be affirmed. But. as to the surety company, tho case is different. It is only liable for a breach of the conditions of its bond. After a careful scrutiny of the provisions of the bond, we find that it does not bind the surety company
ARK.] 649 to refund to the appellee. any money it may have . overpaid to the appellants by reason °If fraud or gross mistake of the engineer. It must be remembered that this is an action by the appellee against the appellants for money whch the appellee alleges had been overpaid to the appellants through the fraud or gross mistake of the engineer. The bond contains no condition whia, upon a breach thereof, would make the surety company liable o appellee for money it had overpaid appellants. The judgment therefore against the surety company is erroneous, and Same will be reversed, and the cause dismissed as to it. As to the 'appellants, the judgment is affirmed.
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.