Cite as 2010 Ark. App. 553 ARKANSAS COURT OF APPEALS EN BANC Nos. CA09-283, CA09-304, & CA09-385 Opinion Delivered JULY 28, 2010 DONALD R. JOHNSON, MARY D. APPEALS FROM THE PUBLIC JOHNSON, and CHARLES MICHAEL SERVICE COMMISSION TURNER [NO. 08-001-U, 08-002-U, & 08-098-U] APPELLANTS V. ARKANSAS PUBLIC SERVICE COMMISSION and SOUTHWESTERN NO. CA09-283 ELECTRIC POWER COMPANY APPELLEES AND WILLIS B. SMITH, JR., and PATTY F. SMITH APPELLANTS V. ARKANSAS PUBLIC SERVICE NO. CA09-304 COMMISSION, SOUTHWESTERN ELECTRIC POWER COMPANY, and AMERICAN ELECTRIC POWER COMPANY APPELLEES AND HEMPSTEAD COUNTY HUNTING CLUB, INC., SCHULTZ FAMILY MANAGEMENT COMPANY, PO-BOY LAND COMPANY, INC., YELLOW NO. CA09-385 CREEK CORPORATION, SCHULTZ FAMILY LIMITED PARTNERSHIP,
Cite as 2010 Ark. App. 553 MARY OBOYLE, and F. PATRICK SCHULTZ APPELLANTS V. ARKANSAS PUBLIC SERVICE COMMISSION and SOUTHWESTERN ELECTRIC POWER COMPANY REMANDED APPELLEES PER CURIAM On November 21, 2007, the Arkansas Public Service Commission (Commission) entered Order No. 11 in Docket No. 06-154-U granting Southwestern Electric Power Company (SWEPCO) a Certificate of Environmental Compatibility and Public Need (CECPN) for construction and operation of a coal fire baseload electric generation facility in Hempstead County, Arkansas (the Turk Plant). That decision was appealed to this court in Hempstead County Hunting Club, Inc. v. Ark. Pub. Serv. Commn, CA08-128. While the Turk Plant appeal was pending, the Commission, in separate dockets, granted SWEPCO additional CECPNs to build transmission lines related to the Turk Plant. The granting of these CECPNs were then appealed to this court in Donald R. Johnson v. Ark. Pub. Serv. Commn, CA09-283; Willis B. Smith, Jr. and Patty Smith v. Ark. Pub. Serv. Commn, CA09-304; and Hempstead County Hunting Club, Inc. v. Ark. Pub. Serv. Commn, CA09-385. Afterwards, the parties to these appeals filed various motions to consolidate appeals, to separate -2-
Cite as 2010 Ark. App. 553 jointly filed appeals, and they sought stays on briefing schedules until their motions were decided. Decisions on these motions were held over by us until the appeal in the Turk Plant was decided, although stays were granted for the filing of briefs in CA09-283 and CA09-304 and, at the Commissions request, for the filing of the record in CA09-385. On June 24, 2009, this court reversed the CECPN granted to SWEPCO for the Turk Plant in Hempstead County Hunting Club, Inc. v. Arkansas Public Service Commission, 2009 Ark. App. 511, 324 S.W.3d 697. Thereafter, the supreme court granted the appellees petition for review of this decision in Docket No. 09-71. In an op inion handed down May 13, 2010, the supreme court reversed the CECPN for construction of the Turk Plant and affirmed as modified the opinion of this court. See Hempstead County Hunting Club, Inc. v. Ark. Pub. Serv. Commn, 2010 Ark. 221, 384 S.W.3d 477. With the reversal of SWEPCOs CECPN for the Turk Plant, appellants in two of the pending appeals have now filed emergency motions to stay the CECPNs previously granted to SWEPCO for transmission lines for the Turk Plant. SWEPCO and the Commission oppose these motions. The motions now pending in this court for disposition are: CA09-283 -Separate appellants Donald R. Johnson and Mary D. Johnsons emergency motion to stay CECPN, filed July 6, 2010, with responses filed by SWEPCO and the Commission. CA09-283 - Separate appellants Donald R. Johnson and Mary D. Johnsons motion to withdraw emergency motion to stay CECPN, filed July 15, 2010. CA09-283 - Appellants motion to consolidate appeals CA08-128 and CA09-283. -3-
Cite as 2010 Ark. App. 553 (Held over.) CA09-283 - Appellants motion to withdraw motion to consolidate with CA08-128, filed July 15, 2010. CA09-304 - Appellants motion to consolidate CA09-304 with CA09-283 and CA08-128. (Held over.) CA09-385 - Appellants emergency motion to stay CECPN, filed July 8, 2010, with responses filed by SWEPCO and the Arkansas Public Service Commission. CA09-385 - Appellants motion to file reply to appellees response, filed July 21, 2010. CA09-385 - Appellees joint motion to separate Arkansas Public Service Commission dockets filed jointly on appeal with response and amended response filed by appellants. (Held over.) In consideration of the supreme courts decision in Hempstead, we hereby remand the above-listed motions and the orders granting the CECPNs that are being appealed in CA09-283, CA09-304, and CA09-385 to the Arkansas Public Service Commission for determination of whether the Hempstead decision nullifies the CECPNs granted in these appeals and for such further orders as the Commission deems necessary. Remanded. -4-
 You are being directed to the most recent version of the statute which may not be the version considered at the time of the judgment.